Belle Haven Country Club
Agronomy Blog – March 26, 2026
Bunker Renovation Update
It’s been another productive week on the course! The construction crew
worked Saturday to install erosion and sediment controls around 16 green,
completing that phase Monday morning. We received approval later that day to
begin demolition.
Joel met with the lead shaper Tuesday afternoon to review this stage of
work, and by Thursday the crew had seven bunkers rough-shaped and ready for
drainage. Joel will return Friday morning to inspect and approve the bunkers
and green surrounds. Once approved, the next step includes installing drainage,
adding bunker sand, and grassing the area. If all goes as planned, we’ll begin
sodding by next Thursday.
Our irrigation team relocated four heads and installed 200 feet of new
pipe to accommodate the bunker work. On Monday, we’ll move another 60 feet of
pipe located beneath one of the new bunkers.
![]() |
| 16 Green bunker renovation taking shape. |
Fairway Aerification
The team also completed fairway aerification this week. Because
conditions were too wet to pull cores, we chose to solid tine and verticut
instead. The fairways cleaned up nicely and received a fresh cut for the
weekend.
![]() |
| Laz verticutting 1 fairway |
If you have any questions, feel free to contact me at maugustin@bellehavencc.com.